Monday, December 16, 2013

Day 142: Landscaping, Railings, Deck, Light Fixtures, POWER!

We might be going to the house every day this week because so much is getting done! We had to go at lunch today b/c we had forgotten those 2 down rods for the girls fans and we had to purchase another garage fluorescent. Originally we were going to go tomorrow but the electricians needed it all today. When we got there we realized we didn't need both down-rods and we have to buy 2 angle fan kits now and take them back in the morning. ahhh!
 
 
We left in such a hurry I only had my phone to take pics...They are kicking some serious butt getting stuff done. My countdown is still set to the latest day we should get the keys which is next Tuesday, Christmas Eve. We are really hoping they give them to us this Friday. It's still up in the air. We will be getting a walk through and our SR told us as soon as our superintendent gives her the go ahead she will call us.
 
 
 Terrible quality pics, I know!
A picture showing the power being hooked up and some of the landscaping

I am super in love with these "Frost Free Gardenias"
Past them will be holly bushes

This guy will be building the entire screened in porch by himself, crazy! I was watching him
hoist this piece of lumber up and it was insane. Apparently he's learned all the tricks to do it by himself.

I couldn't get a straight on shot because there was a car in the way and
the dumpster was still there. If you look closely you can see our crepe myrtle hanging out
in the front yard, waiting on the electric company to move. It will be to the right of the house.
The crepe myrtle will have white blooms to match the gardenias <3

Master Bedroom, Fan and recessed light trim is in!

Garage Side

The posts for the front porch

Columns are almost done in here

Media room recessed lights are in
 
Addison's room and fan
 
 
 

Things to do Interior:

Baseboards/Trim - Still some stuff left
Paint- Touch ups are all that remains and will happen middle of next week
Cabinets-Appliances are in the house, the cut out for the oven/microwave will be fixed soon.
Flooring-Carpet tomorrow
Glass door for shower
Railings-Happened after we left today
Stone around fireplace- not sure
Counters/Faucets-Granite was installed this afternoon after we left
Toilets-Included in trim , week of the 16th after tile is done
Final electrical installs- Today through Wednesday
Window in dining room needs to be replaced
Paint/Stain the front door-Will be stained probably during the final touch ups.

Things to do Exterior:
Exterior trim
Gutters
Paint Exterior
Stonework/Pillars/Fill in porch-Happening today and probably tomorrow and Wednesday
Landscaping-Halfway done
Screened in porch-Now until Wednesday
Mailbox

Sunday, December 15, 2013

Days 140-141: Hardwood Flooring, Closet systems, Grout in tile, Mantel

 
 
We are moving right along. We took all the lights and bulbs we've purchased to the house today. We had to separate it all, label it and put it in it's nearest designated spot. The lights we bought using our credit will be picked up directly from the lighting center tomorrow or Tuesday. We did forget our down rods (boo!) so I have to take them out there tomorrow. I also miscalculated and I was short a few bulbs in the correct wattage/style.
 
The GREAT part was that ALL of the hardwood is installed! It's amazing! It was covered for the most part so I could only see it in sections around the perimeters of the rooms. Everything was pretty dusty too, I took pictures but they aren't the best because of the dust. We went about 3:00 and I could get an idea of where the sun would shine in on the house...I'm definitely going to have window treatments up soon. Addison's room and our room both get a ton of light and it was blinding! I may purchase some of those light filtering temporary blinds until I know what I want to use exactly.
 
The lumber has been delivered for the deck/porch. We are supposed to have a completely rain-free week this week which is good. The landscaper showed up at the house when we were there to tell us he was scoping it out to see how many plants to bring. He said he'll be back tomorrow and should finish up on Tuesday. We get sod in the front and hydro-seed in the back. He made the comment that "there was going to be like 200 subs at the house tomorrow" which tells me it's going to super packed with people trying to finish up. Our SR told us it's going to be crazy busy but that the good thing was everything that was left normally only takes the trades a few hours to do...it's just a matter of getting them there. The exterior still hasn't been painted and no stone work has been done. Very surprising, until I remember how rainy it was on Saturday.
 
 
In a somewhat random order:
 
Most of the closet systems have been installed. Guest room closet

Lumber is delivered for porch


Family Room

Master shower has been grouted, looks really good

Vinyl in the girls bathroom


Girls vanity, vinyl has been covered

Lanie's Room
 
 
 Lanie's Closet
 
Addison's Room-See that sunlight? bright!

Addison's closet, Jack and Jill bath to the right of the picture
 
Master-I love how they painted inside the tray

 
Vinyl in the laundry room

Laundry Room-I'm sure I took the picture crooked.

Media room looking into hallway
 

Hallway looking into media room

Living room into kitchen

 
Mantel has been hung
 

Butlers pantry area

Dining room


Downstairs bath tile; not a great picture. Very dusty.

Linen closet in downstairs bath

Stoop filled in, so glad

I love how they did the corners of the steps, looks like a leaf

From "The Spot"- The dumpster is being removed tomorrow


 
 
 
Things to do Interior:

Baseboards/Trim - Still some stuff left
Paint- Touchups are all that remains and will happen middle of next week
Cabinets-Appliances are in the house, the cut out for the oven/microwave will be fixed soon.
Flooring-Carpet next Tuesday 12/17
Glass door for shower
Railings
Stone around fireplace- not sure
Counters/Faucets-not sure
Toilets-Included in trim , week of the 16th after tile is done
Final electrical installs- Monday December 16th
Window in dining room needs to be replaced
Paint/Stain the front door-Will be stained probably during the final touchups.

Things to do Exterior:
Exterior trim
Gutters
Paint Exterior
Stonework/Pillars/Fill in porch-Happening today
Landscaping-Monday-Tuesday 12/16-12/17
Screened in porch
Mailbox

Friday, December 13, 2013

Days137-139: Tile Shower/flooring , Concrete for driveway/walkway/stoop and more!

Moving right along and I'm so excited! I haven't seen all this in person, my husband went out yesterday and my father in law went this morning. I will be going on Sunday to deliver all the lights/fans/light bulbs.


All of the concrete has been poured! This includes the stoop, the walkway, driveway and back porch. We weren't sure how much they were going to pour around back and it looks like they only gave us a little bit of a landing. We have decided to put some pavers down to make a larger area. We'll probably do this shortly after moving in. The driveway looks great, I am glad they put those angled corners in where it meets the road. The stoop; I am SO glad that huge hole is gone. They built up a sort of scaffolding to support the concrete.

Today all the stone is being installed on the outside and the inside around the fireplace. The same workers are installing our brick steps right now as well. Landscaping is supposed to be happening later on today!




This is where we'll be adding pavers later on
 
All of the tile has been laid! They still have to grout, I can't wait to see this in person.
 
This is the downstairs guest bathroom, I like this color its a grey-ish brown.
 
 
I *think* all the trim is done. I'm not 100% sure but they uncovered all the columns and wainscoting.


I see the grate on the ceiling for the HVAC which means the units are probably set up outside!

More trim that I flipping love.


---------
 
OMG I am dying right now! Hubby took these pics below of our bathroom and shower.

*angels singing* seriously love this. I'm so glad they did a brick pattern in here like on the floor!

I love how the mosaic breaks up the floor and shower a little bit!

eeek! I love the brick pattern. These are 12''x24'' tiles.
 
 
----------
 
This weekend the porch is being built, might be pushed over til Monday because tomorrow it's supposed to rain a lot. The carpet goes in next Tuesday. The vinyl is in the laundry room and girls bathroom already. The lights/fans will be installed next Monday. The hardwoods are going in today as well! Granite is going in today.
 
 
 
Things to do Interior:

Baseboards/Trim - To be finished over the weekend and after all flooring is laid
Paint- Touchups are all that remains and will happen middle of next week
Cabinets-Appliances are in the house, the cut out for the oven/microwave will be fixed soon.
Flooring-Vinyl and tile is laid. Hardwood starts today. Carpet next Tuesday 12/17
Shower Tiled- Tile is set, grout to be finished
Railings-Probably next week
Stone around fireplace-Happening today
Counters/Faucets-Being installed today
Shelving-Included in trim , week of the 16th
Toilets-Included in trim , week of the 16th after tile is done
Final electrical installs- Monday December 16th
Window in dining room needs to be replaced
Paint/Stain the front door-Will be stained probably during the final touchups.

Things to do Exterior: All of this is to be done the week of December 9th-14th
Exterior trim
Gutters
Paint Exterior
Stonework/Pillars/Fill in porch-Happening today
Landscaping-Today
Screened in porch-This weekend
Mailbox

 

Things we need to do:

Call to have the electricity and water switched into our name around the 20th

Freak out about moving into the house the weekend before Christmas, YAY!

Buy the final light bulbs-going tonight!

Wednesday, December 11, 2013

Kitchen Cabinets-A-ok!

I got an email this morning from my contact that the cabinets are delivered that way and will be fixed and re-trimmed when the appliances are installed by the cabinet installers. Whew! Feeling so much better!

If you don't know what I'm talking about look at my previous post.


I failed to add the "to do" list at the end of yesterdays post so I'm going to do it now:


Things to do Interior:
Baseboards/Trim - To be finished over the weekend and after all flooring is laid
Paint-As of 12/11 , it seems all touch ups are done and another coat on the walls will be next
Cabinets-Installed. The oven built in will be fixed when appliances are installed
Flooring-Backer board is installed in bathrooms. Vinyl and tile materials are in the house as of 12-11
Shower Tiled-Backer Board is installed as of 12-11
Railings-
Stone around fireplace-Selected and not sure when this will be done, maybe the week of the 16th
Counters/Faucets-Layout is finished, waiting on installation
Door hardware- Installed
Shelving-Included in trim , week of the 16th
Toilets-Included in trim , week of the 16th after tile is done
Final electrical installs- Monday December 16th
Grates installed-Included in trim , week of the 16th
Appliances - Being delivered Thursday December 12th
Window in dining room needs to be replaced
Paint/Stain the front door-Almost done as of 12/11

Things to do Exterior: All of this is to be done the week of December 9th-14th
Exterior trim
Gutters
Paint Exterior
Stonework/Pillars/Fill in porch-Selected stone Friday 12-6-13
Final Grade-Completed as of 12-10
Landscaping
Screened in porch
Cement for walkway and garage/driveway
Cement for patio
Mailbox
Install water heater/hvac/etc..

 

Things we need to do:

Call to have the electricity and water switched into our name around the 20th

Freak out about moving into the house the weekend before Christmas, YAY!

Buy the extra light for the hallway, buy 13 more light bulbs (just haven't bit the bullet yet) and exchange the down rod.

 
 

Tuesday, December 10, 2013

Days 133-136: Kitchen Cabinets, Bathroom cabinets installed! More Trimwork and Flooring

It was pitch black when I made it to the house; I am thankful my flash worked well so I could get these pictures! There were workers there but they were concentrating on other areas of the house so I couldn't use their light much!
 
As I was pulling up the grader was there and had completed the final grade on the yard. Poor guy; it was mucky red mud everywhere. He was nice and set some wooden boards down for my daughter and I so we didn't get mud all on our shoes.
 
The painters were inside about to start on their last coats. I could tell all the touch ups had been done because of all the markings on the wall. One guy was sanding the walls again in the master bedroom. They had covered up all the trim so they must be done with it! The ceiling over spray was still on the walls so they must be saving the wall touch up until the very end.
 
They also finally filled in the stoop! It was about 13 feet down. They filled it with a metal scaffolding like material and will lay concrete over that.
 
The tile for our bathroom was in the dining room along with all the grout and the mortar. I also spotted the vinyl for the girls bathroom and the laundry room. There was already backer board in our bathroom and in the downstairs bathroom.
 
-----
Starting in the kitchen. The built in oven cabinet is wrong. They built it for a single wall oven; there is no way my double microwave/oven will fit into that small opening. I have left my contact a VM. I really hope this doesn't hinder our closing date :( There are also supposed to be glass doors in the corner cabinets, those may come later. Other than that hiccup they look really great!
The range hood will be in the opening straight ahead. I am not centered in this shot.

Wrong opening; but I love the drawers.


Butlers pantry area.

My Vanity

Husbands vanity

Girls jack and jill bath. I love their vanity; it is so long

Trim all wrapped up in the media room

See all the touch up spots? They covered the trim up on bottom. I love this feature
 
 
 
The husband is going back on Thursday to get another update; I won't be able to go back until Sunday. Can't wait to see the difference!

We picked our granite layout today!

Today was fun. At lunch, the husband and I went to the granite yard and made the layout for our granite! The designer had cut out thick paper and taped it together to show us where the seams would be for our counter top. We were able to show him what areas in the slabs we wanted to avoid and what areas we wanted to showcase, pretty cool!

We will not be using the big orange section in the left top corner. Most of our counters are on the right side. They used a twin set of granite, one piece cut right after another so our seams will match up and be 'seamless' :)


We were able to avoid the big orange globs on both pieces of granite, yay! There will be a total of 3 seams, I'm not thrilled about that, but there's really no way around it. He was very interested in our opinions and we have been told he is such an artist and he makes the seams match up so well. I'm very happy about that! I am not sure when he's planning on cutting and installing but it will be soon.

I'm heading up tonight to see the cabinets, can't wait to see those! I'm also wondering what they've been able to do on the exterior, most of the work that remains is on the outside of the house. It's been raining for days here so who knows what they were actually able to do. Will update tonight :)