Friday, December 6, 2013

Days 131-132: Details and GREAT news!!

I am feeling much better today. Our meeting this morning went very well and I really feel like the builder is trying to make us happy and stay on top of things. I had my phone for pictures so they aren't the best quality. When I go next time I'll take my good camera.

We started by picking the stone, which was more of them hoping we liked the only selection they had. The stone guy brought in a hearthstone and about a 3ft by 1ft section of rock. I was thinking we would have selections to pick from but...no. He had 2 other color choices but didn't bring them. Oh well, it's ok; it's very neutral and that's what we need so I'm letting that one go. The stone will be around the fireplace and on the front of the house. We addressed the hearth issue and that will be taken care of. They have to frame out the bottom of the hearth to wrap around the sides of the fireplace.

The stone choice and the Hearthstone up top


We then moved to the upstairs media room. They have to cut the hole out for the conduit that was previously run from the electrician, they said no problem.

The master bathroom shower will be tiled next week and we needed to make sure they remembered to build a soffit (I think that's the name) down to make it more enclosed; they said yes they will use a special cement board for that.

We brought our down-rods for the girls rooms and we have to go exchange (again) for a different size. Dang-it! Back to Lowes I go. I also have to get one more light for the basement stairwell, just a plain flush mount will do.

We went to the basement to address the cracks. We were told they were completely normal. They could seal them but they would look the same and that it's nothing to worry about.


The best news is that we are back on schedule to hopefully get the keys on Friday December 20th. It may be pushed back to Monday the 23rd depending on delays. What this means is that next week is going to be ridiculously busy. Every crew you can imagine will be working. They will also be locking the doors and they won't give me a key, pretty bummed about that. Vanessa will have to meet me there when I want to go look at everything; or she said if a crew is out there they'll leave it unlocked for me.



Master Bedroom filled with doors!

Living Room, The columns should be completed today, they had to wait
for the coffered ceiling to be done so they could work around the trim

My dining room! I love love love this trim so far; it looks so amazing!


Another view of the dining room corner, I love how this area looks with the
 trim against the windows and the columns!

Muddy mess, it's been rainy all week and it was everywhere. Nothing has changed
 on the outside but that's about to change next week.
 
Our granite slab with its twin behind it. The name is Typhoon Bordeaux. There is lots of orange in the top left corner; we are going to do a layout with the company so we can make sure that falls at a good place in the kitchen layout. The granite is a little lighter overall than this pictures depicts, it was wet in the warehouse.
 
 
 
------------
Timeline (so happy about this)
 
Things to do Interior:Baseboards/Trim - To be finished over the weekend
Paint-First coat done, touch ups will be happening at the end of next week and weekend
Cabinets-Installing Monday
Flooring-All to be started next Wednesday and worked on until the next Sunday
Shower Tiled-In with the above
Railings-The guys were putting the supports in for this yesterday-Next week
Stone around fireplace-Selected and not sure when this will be done, maybe the week of the 16th
Counters/Faucets-Template being taken Monday afternoon, we need to go Tuesday to pick layout
Door hardware- Included in trim , week of the 16th
Shelving-Included in trim , week of the 16th
Toilets-Included in trim , week of the 16th after tile is done
Final electrical installs- Monday December 16th
Grates installed-Included in trim , week of the 16th
Appliances - Being delivered Thursday December 12th
Window in dining room needs to be replaced
Paint/Stain the front door-Probably to be finished when exterior is done which is the week of Dec 9th

Things to do Exterior: All of this is to be done the week of December 9th-14th
Exterior trim
Gutters
Paint Exterior
Stonework/Pillars/Fill in porch-Selected stone Friday 12-6-13
Final Grade
Landscaping
Screened in porch
Cement for walkway and garage/driveway
Cement for patio
Mailbox
Install water heater/hvac/etc..
 
Things we need to do:
Call to have the electricity and water switched into our name around the 20th
Touch base with the lighting company who ordered our vanity/closet/hallway lights-Emailed 12-6
Call the granite company on Tuesday December 10th to choose the layout for the counters
Freak out about moving into the house the weekend before Christmas, YAY!
Buy the extra light for the hallway, buy 13 more light bulbs (just haven't bit the bullet yet) and exchange the down rod.
 
Something that may help fellow readers:
I have set up a "Subscribe and Save" Order with Amazon to be delivered to the new house shortly after we move in. If you don't know about this you need to look in to it! My order consists of trash bags, toilet paper, paper towels, cleaner etc.. These are things I know we are going to need and I don't have space to store them right now. Plus if you set up a delivery of 5 or more items you get 20% off . The items are shipped for free and you can cancel anytime you want. A lot of items also include a coupon code, you just have to look for them. For those with small children: diapers, wipes, lotions, body wash etc.. are also included and you can get some really great deals if you keep up with it!
 
 
I'm not sure when we will go back, maybe next Wednesday and we'll see the cabinets installed for sure! I can't wait!!
 
 

Thursday, December 5, 2013

Days 125-130: Paint, Trim, Picking out granite slab

The interior is painted, it's gorgeous. It really makes it look livable now! The trim around the coffered ceiling makes me drool. I couldn't go up to the second level because there were workers flying around everywhere and I didn't want to disturb them. I tried to get some pictures but because they had the windows taped up, they aren't great. I'll add what I took but they aren't spectacular ;)

You can tell the sprayed the walls first, then sprayed the ceiling and the trim. There was a man there who was marking imperfections in the paint/drywall. He was carrying a huge flashlight and he had a pencil that was about 2 feet long and writing everywhere, even on the ceilings! The doors were off the hinges and had been painted.

We go back in the morning to pick the stone out for the exterior and for the fireplace. We go today at lunch to pick our granite slab out. The lady at the granite place told us they would get their template as soon as the cabinets are in and prepare shortly after, she told me they don't take hardly any time. (great news) We scheduled our appliances to be delivered to the house next Thursday.


Terrible, I know! There was no light and lots of dust flying around


Cove in the office/family room


Trim along coffered looks really great


Things to do Interior:
Baseboards/Trim -In the works still
Paint-First coat done
Cabinets-Scheduled to be installed next week
Flooring-Vinyl/Tile to be started this week and hardwood next week
Shower Tiled-In with the above
Railings-The guys were putting the supports in for this yesterday
Stone around fireplace-picking tomorrow, Friday 12-6-13
Counters/Faucets-Picking slab today
Door hardware
Shelving
Toilets
Final electrical installs (fans/light)
Grates installed
Appliances delivered Scheduled for Thursday December 12
Window in dining room needs to be replaced
Paint/Stain the front door

Things to do Exterior:
As of 12/4/13- nothing has changed on the exterior-It has been very rainy
Exterior trim
Gutters
Paint Exterior
Stonework/Pillars/Fill in porch-Picking stone Friday 12-6-13
Final Grade
Landscaping
Screened in porch
Cement for walkway and garage/driveway
Cement for patio
Mailbox
Install water heater/hvac/etc..

Monday, December 2, 2013

Timeline Update

I've said it before on this blog, probably several times. Our builder is very unorganized. As of last Monday November 25th, we were "on track" to be in before Christmas. We have been saying we needed to be in before Christmas since we started this build. I honestly didn't care if before Christmas meant Christmas Eve!

This morning I get an email that it's unrealistic for us to be in before Christmas. Their contractors are 'just busy'.

Are they unaware that they are in the construction business, and they that they rely on contractors? And that contractors need to be scheduled to work ahead of time? They just don't have a timeline/schedule/list etc! It's so ridiculous that this is happening. So who knows what's going on now and what we are at.

My husband called a few minutes after we got the email and of course NO answer. He left a voicemail. We want a timeline, a schedule, SOMETHING to go off of here. We've been floating for these past 5 months not knowing what's going to next. I really don't think the builder knows. They seriously suck .

Am I over exaggerating to want to know what stage we are in and what's going on? I feel like I am sometimes but then I think, hey I'm paying for this house and I deserve to know. I feel like we are past the point of 'trusting' the builder to get it done...and I feel like we are being taken advantage of.

Days 121-124: Trim and baseboards for Thanksgiving

We drove out to the house yesterday with lots of our family and friends! It was really fun. My brother and sister in law haven't seen it at all. We also met up with Kellie who blogs her house build at http://ournewhomeflorence.blogspot.com/ and her husband. They built their home and it's about 15 minutes from where we are currently living, we've made great friends with them!

Sadly, there was still no paint on the walls, but they had completed a lot of the baseboards and trim. They had the coffered ceiling completely trimmed in the crown moulding and all but 3 of the columns were trimmed too. The dining room still needs the trim package and there are a few areas that still need baseboards.


Updating my list, lol still lots to do in 3 weeks.

Things to do Interior:Baseboards/Trim -Almost done
Paint
Cabinets
Flooring
Shower Tiled
Railings
Stone around fireplace
Counters/Faucets
Door hardware
Shelving
Toilets
Final electrical installs (fans/light)
Grates installed
Appliances delivered (this is on us, they are sitting in Lowes)

Things to do Exterior:
Exterior trim ( idk what it's called but under the roof overhang)
Gutters
Paint Exterior
Stonework/Pillars/Fill in porch
Final Grade
Landscaping
Screened in porch
Cement for walkway and garage/driveway
Cement for patio
Mailbox
Install water heater/hvac/etc..



 
These will be decorative too

It's hard to tell but the crown moulding is in the coffered areas

Foyer

 

My little bro in Addison's room

The columns. I love these! They fill in the space nicely.


Took me a few days to get this post up...going to post an update next.

Monday, November 25, 2013

Days 113-120 Exterior & Drywall Completed & Doors/Casings installed

There wasn't too much fun stuff going on this past week, I had hoped to see paint on the walls...but nope. The exterior is all finished except for painting and stonework. The drywall is completely done and looks really great. I didn't see any places that needed to be touched up so that's a plus. They had installed all the doors and the casings around the windows. All the baseboards and trim pieces were sitting in the living room, there was a ton! I'm assuming they'll put all the trim up and baseboards up and then paint.

I asked when I needed to pick our stone out and they said "in a few weeks" That seems to be cutting our deadline of Christmas really close. We are at 29 days today. *nerve wracking* As of today we are still on track though to be in, according to our SR.

There are just a few things that are wrong:
  • Our fireplace was supposed to be wrapped with a ledge completely around the base. They have to add the framing for it still, I brought it to their attention.
  • The dining room window is still broken and needs to be replaced.
  • The electrician installed conduit in our media room, I need to make sure they cut out the drywall for the box.


------------------------------
Couldn't find my memory card so the pics are from my not so great I phone!

All the baseboards and trim in the living room

Master bedroom doors

Foyer

Lanie's Windows

All hardi-board is up

"The View" Sorry, it was freezing so I was a tad crooked! ha!



Things to do Interior:
Baseboards/Trim (Coffered ceiling crown/Dining room moulding and crown/9 decorated columns)
Paint
Cabinets
Flooring
Shower Tiled
Railings
Stone around fireplace
Counters/Faucets
Door hardware
Shelving
Toilets
Final electrical installs (fans/light)
Grates installed
Appliances delivered (this is on us, they are sitting in Lowes)

Things to do Exterior:
Exterior trim ( idk what it's called but under the roof overhang)
Gutters
Paint Exterior
Stonework/Pillars/Fill in porch
Final Grade
Landscaping
Screened in porch
Cement for walkway and garage/driveway
Cement for patio
Mailbox
Install water heater/hvac/etc..



We found out there are now 5 houses that will be starting construction in the next few months! We will have neighbors on both sides of us soon. I'm excited to see what kind of house they will be building....not so excited about the construction phase.

Saturday, November 16, 2013

Days 110-112: Windows completed/ Drywall Almost Done / Failed Inspection

The last two windows have been installed! So happy that's done and I love the triple window in the front! The siding isn't completed; it looks like they have 2-3 days worth left. The back is almost done as well as the left side. All that's left on the front is the 2 gables with Shakes; I saw the shakes laying in the front yard so those will probably be done first.

There was a note posted on our inspection sheet that said "Seal boxes in envelope" This had yesterday's date on it; and looks to be the only thing they need to do in order to get the power turned on permanently. I wonder what that means? I can only think of the caulking around the windows. Those last two windows they just installed were not caulked so maybe that's it and we will have power in a few days. Then the "finals" begin!

I think the first of this week will be drywall repair; I noticed lots of imperfections. The last of this week should mean painting and trim! This is when it will get fun.

Pics are below, nothing majorly different from Wednesday, well other than the drywall but you can't really tell that in the pictures! I probably won't go back until next Sunday; because this is my final week of school for this semester and I have lots of studying to do.


Triple window, loving it!


Girls enjoying their new steps, blurry pic :(

My Favorite View of The House

Friday, November 15, 2013

Rate is Locked!

Whew! I have been waiting for this moment since March, haha. So stressful throughout this entire process! When we started, like a lot of you guys; the rates were around 3.50%. We locked today at 4.375%. I am happy with this. I thought I was locking at 4.50% but my loan officer called me and caught them in a random dip this afternoon. Sooooooo thankful! We locked in for 60 days and have to close by January 14th.
 
This is great, we can move in over the holidays and things will have
 time to settle down before closing.
 
 
I'm off tomorrow so I'm going to run over to the house to see what happened these last couple of days; will post tomorrow.